The Kentucky Avenue Bridge construction will occur beginning February 2021 through February 2022. Below is a general phase schedule of the construction:
February - April 2021
Phase 1: Mobilization, Preparation & River Sheet Pile Wall
April - June 2021
Phase 2: Caissons / Piers & Trail Sheet Pile Wall
April - May 2021
Phase 3: Ramp Sheet Pile Wall
Mid-May - June 2021
Phase 4: Abutments & South Sheet Pile Wall
July - August 2021
Phase 5: Girders & Deck Pour
August - September 2021
Phase 6: Road Tie-Ins
Mid-August - November 2021
Phase 7: Finishing
February - April 2021
Phase 1: Mobilization, Preparation & River Sheet Pile Wall
April - June 2021
Phase 2: Caissons / Piers & Trail Sheet Pile Wall
April - May 2021
Phase 3: Ramp Sheet Pile Wall
Mid-May - June 2021
Phase 4: Abutments & South Sheet Pile Wall
July - August 2021
Phase 5: Girders & Deck Pour
August - September 2021
Phase 6: Road Tie-Ins
Mid-August - November 2021
Phase 7: Finishing